Cabinari trade supply
Cabinet sourcing for New Zealand
Prepare millimetre cabinet drawings, packing descriptions and final delivery instructions.
What to specify
Share cabinet material and packaging descriptions with the importer. Confirm the receiving postcode, unloading equipment and storage space before approving the shipment plan.
Work back from the required arrival date
Send drawings in millimetres, the receiving location and the date the cabinets must be available on site. If the crew can receive only during specific windows, list those windows separately from the installation date.
| Milestone | What to confirm | Who provides the timing |
|---|---|---|
| Final delivery | Receiving address, unloading appointment and access for the delivery vehicle. | Receiving team and local carrier |
| Import clearance | Entry documents, inspection arrangements and release plan for the shipment. | Importer and customs broker |
| International transport | Routing, booking cutoff, departure and estimated arrival. Reconfirm capacity during peak periods. | Freight forwarder or carrier |
| Order release | Approved drawings and samples, cabinet quantities, packing list and cargo readiness. | Buyer and supplier |
Record the route and date of each estimate. Recheck the dates when equipment, shipment size or the receiving location changes. For phased projects, keep a separate milestone list for each release.
- Cabinet ordering
- Cabinet packaging
- Import document checklist by market
- Cabinet import documentation
- Kitchen cabinet catalog
Related guides
Review the cabinets and packaging separately
| Review | What to check | Who checks | Records to prepare |
|---|---|---|---|
| MPI wood products guidance | Identify the import health standard that applies to the actual cabinet materials and origin. | Importer with its broker | Material and origin schedule, plus any evidence required by the applicable standard. |
| MPI wood packaging guidance | Check pallets, crates, spacers and dunnage, including whether the applicable standard calls for treatment and marking. | Importer and packing supplier | Packing material list and any applicable marks or treatment records. |
Send the importer the cabinet material schedule and packing proposal before packing starts. Record the proposed port, final delivery postcode, receiving hours and unloading method. Ask the freight forwarder to confirm the sailing and arrival estimate for the booked route.
Schedule the shipment from packing to final delivery
| Milestone | Date or detail to confirm | Who confirms it |
|---|---|---|
| Ready to collect | Packing completion, carton count and gross weight. | Supplier |
| Port departure | Origin port, booking cutoff and scheduled sailing. | Freight forwarder |
| New Zealand arrival | Discharge port, any transfer and estimated arrival date. | Freight forwarder |
| Release and delivery | Clearance status, unloading equipment and delivery appointment. | Importer, carrier and receiving team |
Work backward from the receiving appointment. If the site has limited storage, ask the receiving team when it can accept the full load and whether cartons should be grouped by building. Confirm the route and dates against the actual booking before scheduling installers.
Coordinate cabinet sizes with the local trades
Use one dimensioned elevation for the cabinet supplier, installer and worktop supplier. Mark the finished wall, floor level, finished end panels and appliance model numbers. Give the installer the clear width at the narrowest point and show which fillers will be trimmed on site. Where a range or refrigerator sits between cabinets, confirm the manufacturer’s installation clearances and record them separately from the nominal appliance width.
If a sink, tap or worktop is sourced locally, share the model drawings before approving the cabinet schedule. Show the trap and shutoff valves beside drawer boxes and runners, and identify any access panel the installer needs. Assign responsibility for each cutout and record when the final site measurements will be available. This gives the installer and worktop supplier the same reference when they review the order.
Check the receiving plan before approving the packing list
For direct delivery, ask the site team to check vehicle access, the unloading area and the route from the vehicle to the rooms. Where a depot will split a load, send the depot the room schedule and mark which packages must stay together. Record any replacement fronts or hardware separately so the receiver can locate them without unpacking the main order. At handover, compare the carton identifiers with the list and record damaged or missing items by cabinet reference.
For installations involving several trades, record when each room will be ready for measurement, delivery and fitting. Ask the worktop supplier whether it needs to see the cabinets fixed in position before preparing its template. Put the appointment and contact on the same schedule as the cabinet delivery. If the site cannot receive all cartons at once, agree where the remaining units will be stored and who will arrange the next delivery.
Prepare the order by delivery location
For a distributor, group repeat cabinet sizes by stock reference and keep replacement fronts identifiable. For a builder, record the building, unit and room on the schedule. For a renovation, measure the finished opening again before releasing any custom fillers or panels.
Frequently asked questions
- Which units should I use on the cabinet schedule?
- Use millimetres consistently. Dimension the finished opening, cabinet boxes and appliance clearances separately.
- What should I send the importer before packing?
- Send the cabinet material and origin schedule and a separate description of pallets, crates and other wood used to secure the shipment.
- How do I check a proposed arrival date?
- Ask the forwarder for the booked route and estimated arrival, then allow separately for clearance and the final delivery appointment.
- How should cartons be labelled for repeated rooms?
- Agree a building, unit and room reference, then identify mirrored layouts and any hardware packed separately.
- Who measures for a worktop supplied locally?
- Agree who takes the final measurements and when the cabinets will be ready for that visit. Give the worktop supplier the appliance and sink references.
- What do I include in a quote request?
- Send drawings, quantities, finish references, packing preferences and the receiving postcode.
Use the drawing checklist, the quote checklist and the packing guide to prepare the order.